UTILITY DESIGN ACID/BASE

Fast, Flexible, High Quality and On Budget

BACKGROUND

  • Existing acid / base system had reached end-of-life

  • Not compliant with latest EHS standards

  • Frequent break downs

  • Inadequate

Benefit

  • 5 months full project time (CD to Handover

  • 14 days on-site construction time incl. teardown

  • Full interim supply

  • 7.0 MDKK below competitors estimate

  • Ergonomics and maintenance optimized using 3D-modelling in design phase

  • Highest EHS standards achieved

  • Double wall tanks and piping in PE

  • Pump unloading rather than pressurized transfer

  • Unloading capacity increase by 50 % (20 m3 < 20 minutes)

  • Robust distributions pumps

Services

  • EPCMQ

  • Project management (reporting to StC)

  • Full engineering and design package

  • Procurement and contract management

  • Construction management

  • CE marking

  • EHS screening

  • Supporting environmental approvals

  • C & Q test & documentation

  • Handover to line-of-business