PURFIED WATER SYSTEM FOR QC-LABORATORY (2).JPG

PurIfied Water system for QC-laboratory

Fast, Flexible and On Budget

BACKGROUND

  • Ensure capacity and independent supply of Purified Water

  • Existing system with design issues

  • Tight timeline, 20 weeks from kick-off to PQ

Benefit

  • Implementation and documentation of Purified Water system in compliance with authority requirements

  • Qualification including approved PQ within 20 weeks from project start

  • “Base standard system” designed to accommodate client needs and special design requests

  • Coordination/interaction with key stakeholders

  • Delivered within budget

  • Client requirements and adjustments absorbed within timeline

Services

  • Project Management

  • Specification and dimensioning of equipment

  • Dimensioning, design and layout of piping

  • Procurement and Contract Management with external suppliers and contractors

  • Installation supervision on-site

  • Commissioning and system startup

  • Qualification of equipment

  • Maintenance plan and establishing service contract

  • Coordination with client staff: user representatives, technical specialists, management, QA etc.