PurIfied Water system for QC-laboratory
Fast, Flexible and On Budget
BACKGROUND
Ensure capacity and independent supply of Purified Water
Existing system with design issues
Tight timeline, 20 weeks from kick-off to PQ
Benefit
Implementation and documentation of Purified Water system in compliance with authority requirements
Qualification including approved PQ within 20 weeks from project start
“Base standard system” designed to accommodate client needs and special design requests
Coordination/interaction with key stakeholders
Delivered within budget
Client requirements and adjustments absorbed within timeline
Services
Project Management
Specification and dimensioning of equipment
Dimensioning, design and layout of piping
Procurement and Contract Management with external suppliers and contractors
Installation supervision on-site
Commissioning and system startup
Qualification of equipment
Maintenance plan and establishing service contract
Coordination with client staff: user representatives, technical specialists, management, QA etc.